Basin Electric has begun the process to obtain permits to construct and operate its first generating resource in Montana - a natural-gas fueled peaking unit located eight miles northeast of Culbertson, MT. An approximately $100 million project, the unit will be called the Culbertson Generation Station.
The unit will be sited near a compressor station on the Northern Border Pipeline in order to use natural gas from Basin Electric’s subsidiary, Dakota Gasification Company, via the pipeline, to spin its turbine. Basin Electric will be using General Electric’s LMS100® simple-cycle gas turbine to provide about 91 megawatts (MW) of power to the region. Fuel oil is not planned as a “back-up” fuel at this time, but - if required - the turbine is capable of being modified to use fuel oil at a later date.
Dick Shaffer, Basin Electric mechanical engineering supervisor and project coordinator, said several regulatory approvals must be obtained before work can begin, giving an approximate construction start date of the spring of 2009 and anticipated completion by spring of 2010.
Shaffer said a request has been made to interconnect the peaking station with an existing 115,000-volt transmission line operated by Western Area Power Administration. Discussions are under way with Dry Prairie Rural Water for project water requirements, which may require several miles of pipeline from one of its main lines to the Culbertson site.
Culbertson Generation Station is being built in response to the increasing loads of our member-consumers, including those in the Williston Basin.
|
|
|
|
Dick Shaffer, project manager, visits |
Kevin Solie, environmental analyst, |
| Capacity: | 91 MW of peaking capacity |
| Location: | Eight miles northeast of Culbertson, MT |
| Project manager: | Dick Shaffer |
| Fuel: | Natural gas |
| Turbine: | General Electric’s LMS100® simple-cycle gas turbine |
| Project status: | Obtaining regulatory approvals |
| Estimated cost: | $100 million |
| Estimated completion | May 2010 |
Learn More
Richard Fristik
Rural Utilities Service
1400 Independence Ave., SW, Stop 1571
Washington, DC 20250
202-720-5093
Email: richard.fristik@wdc.usda.gov
Greg Hallsten
Montana DEQ
1520 East 6th Ave.
Helena, Montana 59620
406-444-3276
Email: ghallsten@mt.gov
Kevin Solie
Basin Electric Power Cooperative
1717 E. Interstate Avenue
Bismarck, North Dakota 58503
701-355-5495
Email: ksolie@bepc.com
Public comment
Basin Electric, the USDA's Rural Development, and the Montana Department of Environmental Quality hosted a public meeting on the prosposed peaking station near Culbertson, MT, on Feb. 26, 2008.
This public participation effort focused on providing information and gathering input from the public on the new 100-megawatt natural gas-fired combustion turbine Basin Electric proposes to build.